1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
IT-GR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
11-01-2026 09:00 - 10:00 500 MW
11-01-2026 10:00 - 11:00 500 MW
11-01-2026 11:00 - 12:00 500 MW
11-01-2026 12:00 - 13:00 500 MW
11-01-2026 13:00 - 14:00 500 MW
11-01-2026 14:00 - 15:00 500 MW
11-01-2026 15:00 - 16:00 500 MW
5. Amount of LTTR remaining after curtailment:
11-01-2026 09:00 - 10:00 0 MW
11-01-2026 10:00 - 11:00 0 MW
11-01-2026 11:00 - 12:00 0 MW
11-01-2026 12:00 - 13:00 0 MW
11-01-2026 13:00 - 14:00 0 MW
11-01-2026 14:00 - 15:00 0 MW
11-01-2026 15:00 - 16:00 0 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
HVDC cable ARACTHOS – GALATINA
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CC
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication